Checking ultimate bearing capacity is only half the picture when designing foundations on cohesive soils. Saturated clays expel pore water slowly under load, causing long-term primary consolidation settlement. Use our free calculator below—based on Terzaghi's 1D Consolidation / Diffusion Equation and Eurocode 7 (BS EN 1997-1) guidelines—to estimate both total settlement (mm) and how many years settlement will take. Not for professional use, for research only.
When a new building, embankment, or floor slab applies a vertical load onto saturated clay, the load is initially carried by the incompressible water trapped inside the microscopic soil pores (excess porewater pressure). Because clay has very low permeability, water drains out slowly over months or years. As pore water escapes, the clay mineral skeleton compresses—a process known in soil mechanics as Primary Consolidation.
Mathematically, Karl von Terzaghi (1925) proved that 1D soil consolidation is governed by the exact same partial differential equation as Fourier's Heat Diffusion Equation:
∂u / ∂t = cv (∂²u / ∂z²)
From this governing equation, our calculator solves two critical engineering parameters:
Sc = mv × Δσ′ × Ht = (Tv × d²) / cvIn accordance with BS 5930 and BS EN 1997-2, accurate mv and cv parameters are determined by laboratory 1D Oedometer Testing on undisturbed borehole samples (U100/UT100). For early feasibility screening, typical ranges for common UK geological formations are shown below:
| UK Soil / Geological Formation | Typical Compressibility (mv, m²/MN) | Typical Consolidation (cv, m²/yr) | Plasticity & Settlement Risk |
|---|---|---|---|
| Stiff Glacial Till / Boulder Clay | 0.05 – 0.10 | 2.0 – 6.0 | Low Compressibility |
| Firm to Stiff London Clay / Lias Clay | 0.10 – 0.20 | 1.0 – 2.5 | Medium Compressibility (High Shrink/Swell) |
| Firm Weald / Oxford / Kimmeridge Clay | 0.12 – 0.25 | 1.0 – 3.0 | Medium Compressibility |
| Soft Alluvial / Estuarine Clay | 0.40 – 1.50+ | 0.5 – 1.5 | High to Very High Compressibility (Piling/Ground Improvement) |
Hopefully by using this calculator you can quickly check whether long-term clay settlement is likely to exceed structural limits on your development site. If your calculation flags a settlement warning and you require borehole drilling, window sampling, or a formal Geotechnical Foundation Design Report, please call or email Southwest Environmental Limited.
Under BS EN 1997-1 (Eurocode 7) Annex H, standard masonry and framed structures can typically tolerate a maximum total settlement of 25 mm on isolated pad or strip footings, and up to 50 mm on stiffened raft foundations, provided differential settlement does not induce excessive angular distortion (typically limited to 1/500 to prevent cracking in walls and finishes).
Because the drainage path length (d) is squared in Terzaghi's time equation (t ∝ d²), identifying thin permeable sand or gravel seams during a ground investigation is critical. A 4m thick clay layer underlain by impermeable bedrock (single drainage, d = 4m) takes four times longer to settle than the exact same 4m clay layer sandwiched between permeable terrace gravels above and sandstone below (double drainage, d = 2m).
When a Phase 2 Geotechnical Site Investigation identifies excessive primary consolidation or soft alluvial soils, our engineers help developers evaluate cost-effective foundation options:
To save time and mobilization costs, Southwest Environmental Limited routinely combines geotechnical borehole testing (SPTs, triaxial strength, oedometer consolidation, and shrink/swell plasticity index testing) with environmental soil and leachate sampling to discharge both Building Control foundation requirements and Local Planning Authority contaminated land conditions in a single visit.